This is our third Saturday work session. The full test table is getting very crowded.  We built a light weight table so all three teams can get testing. 

We got our scores from the first period documentation.  All teams did well, but not as high as we were hoping for.  A review of the scoring guidelines reveled that almost no one gets the top score of 6 and very few get the high score of 5.  We met all the requirements well, but we need to add more documentation outside the requirements to get high scores.

Topic Team 092 Team 093 Team 196
Initial and Rejected Design Concepts 4/6 4/6 4/6
Project Plan 4/6 5/6 4/6
Simulation and Prototyping for Evaluating Ideas 5/6 4/6 4/6
Program Code 4/6 4/6 4/6
Total for Period 1 17/24 16/24 16/24

We have some stories to tell about our bots>

Team 196

Bot in the Starting Box
Grabbed One Cup
Found Tribble Pile
Sorted Tribble Pile

Team 093

Finding Tribble Pile
Sorting Tribble Pile

Team 092

Bots in the Starting Box
Grabbed One Cup
Grabbed Two Cups
Grabbed Three Cups

 

Copyright 2008 Lockheed Martin Exploring Program
Updated:
April 8, 2008